Success story
He recovered the costs of his 2009 mortgage, with interest
The bank had rejected his claim in writing; taking it to court changed the outcome.
€2,350recovered, plus interest from the day he paid them
Situation
He signed his mortgage in 2009 and paid the notary, Land Registry, administrative agency (gestoría) and valuation costs in full, as banks required at the time. He complained on his own to the bank's customer service department and received a written refusal arguing that the claim was time-barred.
What was done
The lawyer gathered the original invoices, recalculated what could be claimed under the case law of the Spanish Supreme Court and the Court of Justice of the European Union on the limitation period, and filed the claim with the specialist court in Zaragoza, asking for the bank to be ordered to pay costs.
Outcome
The judgment ordered the bank to refund €2,350 plus statutory interest from the date of each payment and to pay the legal costs. The client did not pay any fees upfront: they were taken from the amount recovered and from the costs awarded.